ADDRESS: 19802 Placerita Canyon Rd Newhall, CA 91321
TIME TAKEN TO COMPLETE: 128 days
ZERO TIME LOST INCIDENT RATE: Over 500 plus workers on-site with zero accidents
HIGHLIGHTS: Completed the project on time with a zero-punch list.
PR was asked to take over the project at the last minute to complete it on time for several movie deals that could not push. The project consisted of completing six half-completed buildings for a movie set and built and completed the remaining seven buildings.