ADDRESS: 3355 E La Palma Ave, Anaheim, CA 92806

TIME OF COMPLETION: 318 Days

ZERO LOST-TIME INCIDENT RATE: Zero Accidents

HIGHLIGHTS: Integration of spectator seating and amenities, providing a comfortable and inviting space for families and fans to support their athletes.


The scope of this project included the demolition of four residential homes to make way for the construction of an Olympic-size aquatic center. In addition to the aquatic facilities, the project involved relocating nine classrooms to their new facilities. One of the key challenges faced was the constraint of the school schedule, necessitating the completion of the new center before the Water Polo season commenced. Despite these challenges, PR Construction successfully managed the project timeline, ensuring the timely completion of the state-of-the-art aquatic center while meeting all academic and athletic needs of Servite High School.